New Building Progress Report

Minimize

Project description

 

The Phase I Worship Facility is a single story, 22,995 square foot, slab-on-grade, pre-engineered metal building housing a 420 seat sanctuary, a Teen/Haven Room, 5 classrooms, a warming kitchen and administrative area. Site work includes a new common entry/driveway; new access to the three residential lots; 110 parking spaces; front door drop off area; storm water management facilities; and widening and improvements to Old National Pike within the public right-of-way. The total project “all in” budget, including the cost of the land, is $7,242,000.

Progress report

 

January 2011

  • Grading Permit received
  • Site Work Contract awarded to Pleasants Construction
  • Commitment letter from Sandy Spring Bank for $2.5 million loan
  • Building Permit received

 February 2011

  • Site work begun February 4

March 2011

  • Stormwater Management Pond and Facilities completed
  • Mass grading and rock removal underway
  • Construction Contract awarded to Roy C. Kline Contractors

April 2011

  • April 19 - Settlement on construction loan with Sandy Spring Bank

 May 2011

  • Building Pad Ready
  • Kline Mobilization
  • 1st Concrete Placement

July 2011

  • Pre-engineered metal building delivered
  • Underground storm watrer management piping and facilities completed

August  2011

  • Metal building framing erected
  • Installation of the roof insulation and metal roof started
  • Curb and gutter installed
  • Base course of asphalt in back parking lot placed

September  2011

  • Installation of the metal roof and insulation completed
  • Installation of the metal studs for the interior drywall partitions started
  • All four sides around the building seeded and mulched
  • Work on Deccel/Accel land and road widening begun

 October  2011

  •  Rough in installation of both the electrical and plumbing distribution systems begun.
  • Installation of all non-structural metal stud framings completed
  • Exterior dooors in the metal bulding portion installed
  • Near completion on road widening and Deccel/Accel Lanes

 November  2011

  • Installed the main electrical  switchgear and all of the electrical distribution panels throughout the building.
  • Began installing the sound attenuation drywall on all sanctuary walls.
  • Received approval from Fred. Co Planning Commission for Phase 2 & 3 Site Plan
  • Completed the lane stripping for the widened section of Old National Pike
  

Building Our New Church

 

Progress Report

 

Photo Gallery

 

Floor Plan

 

Site Plan

 
 

Our Building Partners

Home   |   About Us   |   Connect   |   Calendar   |   Missions   |   Ministries   |   Contact Us
Privacy Statement    |   Terms Of Use   |    Copyright © 2009 - Damascus Road Community Church - All rights reserved.